Sunday, February 28, 2010

Wet Meadow III - Overview

Wet Meadow III will be just to the south of the paved path from Essex Road to Allen School. As its name implies, it will be the third wet meadow in Buhr Park.

Construction of Wet Meadow III is taking part in two phases: hardscape & grading and planting. Hardscape and grading was completed in the fall of 2009 by the City of Ann Arbor. It will be planted by volunteers on May 23, 2010. More about Wet Meadow III Planting Day.




The overall project is being funding by the City of Ann Arbor as part of the parks improvement millage. The design was done by ECT in Ann Arbor. The site plan is available online. To orient yourself when looking at the site plan - Essex Road is at the left end of the path and Allen School is at the top center.